SACQSP quantity surveying fee calculator
Calculates the guideline professional fee for quantity surveying services under the SACQSP 2024 Guideline Tariff of Professional Fees (Board Notice 741 of 2025, Gazette 52152, 21 February 2025, effective 1 May 2024). The basic fee is taken from the clause 2.2.1 scale, multiplied by the appropriate percentage for the service, and apportioned to stages under clause 2.7.
It handles mixed contracts the way clause 2.1.2 requires: one basic fee on the whole value, apportioned to each category before its percentage is applied, rather than restarting the scale for each part.
Service
The service and category select the appropriate percentage applied to the basic fee, and the clause 2.7 row that apportions it to stages. The tariff does not differentiate by building type or complexity (clause 1.4).
Value for fee purposes
Clause 10.49: the final value of the contract, or a fair estimate, including preliminaries, contract price adjustment and specialist installations, and excluding VAT and contingencies.
Contract make-up
Where one contract includes more than one category, the basic fee is apportioned to each pro rata by value before its percentage is applied (clause 2.1.2). Enter the parts of the value for fee purposes that fall in each.
Work Stages
Specify percentage adjustments for the project or per stage.
Specify which stages and deliverables per stage are applicable. Use the drop-down button next to each stage.
Select the default deliverables under each stage as required. Deliverable percentages are fixed shares of the stage.
Legend: P = Partial service (not all deliverables selected).
| Stage / Deliverable | Weighting | Applicable | Reduction | Guideline Fee | Adjusted Fee |
|---|---|---|---|---|---|
| Default (all stages) | % | ||||
Stage 1 - Inception | 5% | % | R 0,00 | R 0,00 | |
Stage 2 - Concept & Viability | 10% | % | R 0,00 | R 0,00 | |
Stage 3 - Design Development | 15% | % | R 0,00 | R 0,00 | |
Stage 4 - Documentation & Procurement | 40% | % | R 0,00 | R 0,00 | |
Stage 5 - Construction | 25% | % | R 0,00 | R 0,00 | |
Stage 6 - Close Out | 5% | % | R 0,00 | R 0,00 | |
| Total Fee (Excl. VAT) | R 0,00 | R 0,00 | |||
| Fee as percentage of works value | — | — | |||
Summary
Disbursements (clause 8) are claimable in addition to the fee and are not included here.